File #: 18-5498    Version: 1 Name: BID REVIEW - MINT FARM SEWER PUMP STATION VFD REPLACEMENT
Type: Bid Status: Consent Calendar
File created: 7/3/2018 In control: City Council
On agenda: 7/12/2018 Final action:
Title: BID REVIEW - MINT FARM SEWER PUMP STATION VFD REPLACEMENT COUNCIL STRATEGIC INITIATIVE ADDRESSED: Provide sustainable water quality & environmental infrastructure SUMMARY STATEMENT: This project consists of removal and replacement of two existing 150-hp Siemens Robicon Variable Frequency Drive (VFD) units at the Mint Farm Sewer Pump Station on Prudential Boulevard. On June 27, 2018, four bids were received as follows: $129,341.65 - Hamer Electric Inc., Longview, WA $133,233.25 - Advanced Electrical Technologies, Longview, WA $142,364.46 - J.H. Kelly, LLC, Longview, WA $156,745.00 - Northeast Electric, LLC, Woodland, WA $83,000.00 - Engineer’s Estimate All bids received were determined to be regular and responsive and the bidders are licensed to perform the work. The low bid exceeds the engineers estimate by 55.83% and exceeds the budget for this work. Staff believes that rejecting all bids and re-advertising the project to receive new bids will result in lower bid prices. F...
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

BID REVIEW - MINT FARM SEWER PUMP STATION VFD REPLACEMENT

 

COUNCIL STRATEGIC INITIATIVE ADDRESSED:

Provide sustainable water quality & environmental infrastructure

 

SUMMARY STATEMENT:

This project consists of removal and replacement of two existing 150-hp Siemens Robicon Variable Frequency Drive (VFD) units at the Mint Farm Sewer Pump Station on Prudential Boulevard.

 

On June 27, 2018, four bids were received as follows:

 

$129,341.65 - Hamer Electric Inc., Longview, WA 

$133,233.25 - Advanced Electrical Technologies, Longview, WA

$142,364.46 - J.H. Kelly, LLC, Longview, WA

$156,745.00 - Northeast Electric, LLC, Woodland, WA

 

$83,000.00 - Engineer’s Estimate

 

All bids received were determined to be regular and responsive and the bidders are licensed to perform the work.

 

The low bid exceeds the engineers estimate by 55.83% and exceeds the budget for this work.  Staff believes that rejecting all bids and re-advertising the project to receive new bids will result in lower bid prices.

 

FINANCIAL SUMMARY:

This project is funded by the Sewer construction fund.

 

RECOMMENDED ACTION:

Motion to reject all bids received for this project.

 

STAFF CONTACT:

Chris St.Onge, Project Engineer