File #: 18-5432    Version: 1 Name: R.A. LONG PARK PLAZA RESTORATION DESIGN APPROVAL
Type: Agenda Item Status: Passed
File created: 5/3/2018 In control: Public Works
On agenda: 5/10/2018 Final action: 5/10/2018
Title: R.A. LONG PARK PLAZA RESTORATION DESIGN APPROVAL COUNCIL STRATEGIC INITIATIVE ADDRESSED: Address quality of place issues CITY ATTORNEY REVIEW: N/A SUMMARY STATEMENT: On February 8, 2018, the City Council directed staff to pursue a preferred design concept selected by the Council for the R.A. Long Park Plaza Restoration project. The proposed project improvements include: · Construct new upper and lower concrete plaza · Construct ADA ramps on west side of plaza · Construct gazebo · Upgrade four park light standards · Upgrade existing park electrical service · Install two additional power receptacles in the lawn area · Replace some of the defective concrete walkways in the park The proposed design concepts were reviewed and approved by the Historic Preservation Commission, Parks and Recreation Board, Project Longview, and the donor providing funds for the gazebo. A Certificate of Appropriateness application has been submitted to the Historic Preservation Commission for app...
Attachments: 1. RA Long Park Presentation 5-10-18.pdf

Title

R.A. LONG PARK PLAZA RESTORATION DESIGN APPROVAL

 

COUNCIL STRATEGIC INITIATIVE ADDRESSED:

Address quality of place issues

 

CITY ATTORNEY REVIEW:  N/A

 

SUMMARY STATEMENT:

On February 8, 2018, the City Council directed staff to pursue a preferred design concept selected by the Council for the R.A. Long Park Plaza Restoration project.  The proposed project improvements include:

 

                     Construct new upper and lower concrete plaza

                     Construct ADA ramps on west side of plaza

                     Construct gazebo

                     Upgrade four park light standards

                     Upgrade existing park electrical service

                     Install two additional power receptacles in the lawn area

                     Replace some of the defective concrete walkways in the park

 

The proposed design concepts were reviewed and approved by the Historic Preservation Commission, Parks and Recreation Board, Project Longview, and the donor providing funds for the gazebo.  A Certificate of Appropriateness application has been submitted to the Historic Preservation Commission for approval.

 

The project is scheduled to open bids in late July, with construction scheduled to start in late August after the 2018 Squirrel Fest.

 

FINANCIAL SUMMARY:

Project funding includes:

 

●  Kuntz Family Trust = $400,000 ($100,000 allocated to replace defective walkways)

●  State Capital Budget = $287,120

●  Private donation = $75,000 (toward the gazebo)

●  Capital Projects Fund = $44,000

●  Total Funding = $806,120

 

RECOMMENDED ACTION:

Motion to approve the proposed R.A. Long Park plaza project design and direct staff to complete the design and advertise for bids.

 