File #: 18-5350    Version: 1 Name: BID REVIEW - NICHOLS BLVD. WATERLINE REPLACEMENT
Type: Bid Status: Consent Calendar
File created: 2/28/2018 In control: City Council
On agenda: 3/8/2018 Final action:
Title: BID REVIEW - NICHOLS BLVD. WATERLINE REPLACEMENT COUNCIL STRATEGIC INITIATIVE ADDRESSED: Provide sustainable water quality & environmental infrastructure SUMMARY STATEMENT: This project will replace existing deteriorated 6-inch cast iron water main with approximately 1,090 feet of 8-inch and 60 feet of 6-inch ductile iron pipe, reconnect 3 water services, and install 2 fire hydrants. The work will occur on Nichols Boulevard from 20th Avenue to the alley between 23rd & 24th Avenues. On February 27, 2018, five bids were received as follows: $316,877.85 - Catworks Construction, Battle Ground, WA $394,549.22 - Nutter Corporation, Vancouver, WA $408,579.08 - Advanced Excavating Specialists LLC, Longview, WA $445,836.83 - Clark and Sons Excavating, Battle Ground, WA Non-Responsive - NW Construction General Contracting, Battle Ground, WA $350,000.00 - Engineer’s Estimate Four bids received were determined to be regular and responsive. The bid received from NW Construction General...
Attachments: 1. Nichols Blvd Wtr VICINITY MAP
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

BID REVIEW - NICHOLS BLVD. WATERLINE REPLACEMENT

 

COUNCIL STRATEGIC INITIATIVE ADDRESSED:

Provide sustainable water quality & environmental infrastructure

 

SUMMARY STATEMENT:

This project will replace existing deteriorated 6-inch cast iron water main with approximately 1,090 feet of 8-inch and 60 feet of 6-inch ductile iron pipe, reconnect 3 water services, and install 2 fire hydrants.  The work will occur on Nichols Boulevard from 20th Avenue to the alley between 23rd & 24th Avenues.

 

On February 27, 2018, five bids were received as follows:

 

$316,877.85 - Catworks Construction, Battle Ground, WA

$394,549.22 - Nutter Corporation, Vancouver, WA 

$408,579.08 - Advanced Excavating Specialists LLC, Longview, WA

$445,836.83 - Clark and Sons Excavating, Battle Ground, WA

Non-Responsive - NW Construction General Contracting, Battle Ground, WA

 

$350,000.00 - Engineer’s Estimate

 

Four bids received were determined to be regular and responsive.  The bid received from NW Construction General Contracting was determined to be non-responsive because their bid did not include a required acknowledgement of Addendum #2 and they submitted the incorrect Proposal form.

 

FINANCIAL SUMMARY:

This project is funded by the Water Construction Fund.

 

RECOMMENDED ACTION:

Motion to reject the bid from NW Construction General Contracting as non-responsive and accept the low bid and award a contract to Catworks Construction in the amount of $316,877.85.

 

STAFF CONTACT:

Sam Barham, Project Engineer