File #: 18-5431    Version: 1 Name: ENGINEERING SERVICES CONTRACT WITH PBS ENGINEERING AND ENVIRONMENTAL FOR SR 432 / SR 411 INTERCHANGE IMPROVEMENTS PROJECT
Type: Agenda Item Status: Consent Calendar
File created: 5/3/2018 In control: Public Works
On agenda: 5/10/2018 Final action:
Title: ENGINEERING SERVICES CONTRACT WITH PBS ENGINEERING AND ENVIRONMENTAL FOR SR 432 / SR 411 INTERCHANGE IMPROVEMENTS PROJECT COUNCIL INITIATIVE ADDRESSED: Improve transportation systems CITY ATTORNEY REVIEW: YES SUMMARY STATEMENT: State Route 432 is an important regional and interstate freight corridor that carries more than 10 million tons of freight per year and connects Oregon to Interstate 5. The Cowlitz-Wahkiakum Council of Governments, in cooperation with Longview and other local agencies, completed the SR 432 Highway Improvement & Rail Realignment Study (Study) in September 2014. The Study identified Tier 1, Tier 2, and Market-driven improvement projects to mitigate current and future congestion and impacts on the local street network, emergency responders, and travel reliability through the corridor. The SR 423 / SR 411 Interchange Improvements project is identified as a Tier 2 project in the Study. This project will widen the SR 432 off-ramp to add a second left-turn...
Attachments: 1. PBS_ScopeOfWork.pdf, 2. SR432-SR411 Design Concept.jpg
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
ENGINEERING SERVICES CONTRACT WITH PBS ENGINEERING AND ENVIRONMENTAL FOR SR 432 / SR 411 INTERCHANGE IMPROVEMENTS PROJECT

COUNCIL INITIATIVE ADDRESSED:
Improve transportation systems

CITY ATTORNEY REVIEW: YES

SUMMARY STATEMENT:
State Route 432 is an important regional and interstate freight corridor that carries more than 10 million tons of freight per year and connects Oregon to Interstate 5. The Cowlitz-Wahkiakum Council of Governments, in cooperation with Longview and other local agencies, completed the SR 432 Highway Improvement & Rail Realignment Study (Study) in September 2014. The Study identified Tier 1, Tier 2, and Market-driven improvement projects to mitigate current and future congestion and impacts on the local street network, emergency responders, and travel reliability through the corridor.

The SR 423 / SR 411 Interchange Improvements project is identified as a Tier 2 project in the Study. This project will widen the SR 432 off-ramp to add a second left-turn lane from the limited access portion of SR 432 onto 3rd Avenue and the continuation of SR 432, and realign the SR 432 on-ramp to improve the geometry of the ramp and reduce crashes. This project will reduce congestion and improve safety.

In accordance with Washington state law regarding selection of professional engineering services, staff selected PBS Engineering and Environmental as the most qualified firm to provide services necessary for design of this project. The scope of work includes:
· Environmental review and permitting
· Public participation program to review design concepts and construction staging
· Preliminary and final design
· Traffic analysis
· Design support during construction bidding
· Construction management and inspection services are not included in current scope of work and contract amount, but may be added at the time of construction.

FINANCIAL SUMMARY:
In 2016, the City was awarded a $2,100,000 Freight Mobility Strategic Investment Board (FMS...

Click here for full text